Progress
 
 
Project Details
DAR-2024-001137
MSPCLB26
Construction of RR Masonry Retaining Wall at Andro (Uchon) for tower location no, 37 for Kongba to Thoubal 132 Kv line
26/07/2024
POWER (MSPCL)
Imphal-East
12.11
0.00
Demoimp
State Plan
100%
xyz
24.738846557753472,94.03873372077976
Construction of RR Masonry Retaining Wall at Andro
Progress Update : 22/10/2024
100%
xyz
bondsapam
24.738846557753472,94.03873372077976
24.8176815,93.934897
13.664618591636
0
completed