DAR-2024-001043
UKL/Khamasom Khullen to KhamasomPhungdhar/239
Construction of Blacktopping from Khamasom Khullen to Khamasom Phungdhar village
21/11/2023
PWD
Ukhrul
60.00
0.00
State Plan
80% progress
Phase 1
25.21346912731334,94.49890422821079
Widening, GSB,Ring culvert
Progress Update : 27/08/2024
80% progress
Phase 1
eeukld
25.21346912731334,94.49890422821079
25.2154452,94.5009311
0.29974831777374
0
E/W, GSB

Progress Update : 27/08/2024
80% progress
Phase 1
eeukld
25.21346912731334,94.49890422821079
25.2139567,94.4996717
0.094337649315169
0
E/W, GSB

Progress Update : 27/08/2024
80% progress
Phase 1
eeukld
25.21346912731334,94.49890422821079
25.2132455,94.4991861
0.037713196691014
0
E/W, GSB

Progress Update : 27/08/2024
80% progress
Phase 1
eeukld
25.21346912731334,94.49890422821079
25.2112362,94.4991134
0.24916833981682
0
E/W, GSB

Progress Update : 27/08/2024
80% progress
Phase 1
eeukld
25.21346912731334,94.49890422821079
25.2112362,94.4991134
0.24916833981682
0
E/W, GSB

Progress Update : 27/08/2024
80% progress
Phase 1
eeukld
25.21346912731334,94.49890422821079
25.2112917,94.4990933
0.24285318200663
0
E/W, GSB

Progress Update : 27/08/2024
100% completed
Phase 1
eeukld
25.21346912731334,94.49890422821079
25.2107477,94.4992961
0.30515140394331
0
E/W, GSB

Progress Update : 27/08/2024
80% progress
Phase 1
eeukld
25.21346912731334,94.49890422821079
25.210765,94.499315
0.30349706426726
0
E/W, GSB

Progress Update : 27/08/2024
80% progress
Phase 1
eeukld
25.21346912731334,94.49890422821079
25.2084067,94.4995417
0.56653037509851
0
E/W, GSB

Progress Update : 27/08/2024
80% progress
Phase 1
eeukld
25.21346912731334,94.49890422821079
25.2082762,94.4994843
0.58034066500973
0
E/W, GSB

Progress Update : 27/08/2024
80% progress
Phase 1
eeukld
25.21346912731334,94.49890422821079
25.2079907,94.4994365
0.6114929096035
0
E/W, GSB

Progress Update : 27/08/2024
80% progress
Phase 1
eeukld
25.21346912731334,94.49890422821079
25.20596,94.4998017
0.83980393442093
0
E/W, GSB

Progress Update : 27/08/2024
80% progress
Phase 1
eeukld
25.21346912731334,94.49890422821079
25.2057683,94.499525
0.85852602632862
0
E/W, GSB

Progress Update : 27/08/2024
100% completed
Phase 1
eeukld
25.21346912731334,94.49890422821079
25.2014567,94.4997383
1.3382897700259
0
E/W, GSB