Progress

 
 
Project Details
DAR-2020-000312
BD-II/AE-III/T-VII No. 1 CS Bungalow
Renovatn/Repairing of CS Bungalow Qtr.T-VII/No.1 Main Bldg,Extsn of Kitchen,Verandah,Partition wall &Security Barrack,Supply of furniture item at Sanj
28/02/2018
PWD
Imphal-East
61.81
30
2216/05/053/01/02/27
Completed
II
24.802845097123416,93.94404718598325
Main Bldg, Kitchen extension, wallPartition, Security barrack,supplying of furniture items,etc.
Progress Update : 16/03/2020
Completed
II
so1bd2
24.802845097123416,93.94404718598325
24.803301,93.94686
0.28839546593717
30
Furniture Almirah

Progress Update : 16/03/2020
Completed
II
so1bd2
24.802845097123416,93.94404718598325
24.8033013,93.9468598
0.28838146639694
30
Furniture bed

Progress Update : 16/03/2020
98%
II
so1bd2
24.802845097123416,93.94404718598325
24.8032866,93.9468685
0.28896377973507
30
Front elevation Repaired

Progress Update : 16/03/2020
Completed
II
so1bd2
24.802845097123416,93.94404718598325
24.8032866,93.9468685
0.28896377973507
30
Drawing room with Furniture