Progress

 
 
Project Details
DAR-2018-000606
UKL/Road/Nambashi - Tengnoupal/13
Improvement of road from Nambashi Khullen to Tengnoupal Block via Kasom Khullen Block and Yongkhul Village - 16 km.
01/03/2018
PWD
Ukhrul
100.00
50.00
State Plan
Construction in progress
Phase 1
24.60136927857895,94.35635835092148
Earth Work, Roadside drain RCC Ring Culvert NP-3,
Progress Update : 22/03/2018
Construction in progress
Phase 1
eeukld
24.60136927857895,94.35635835092148
24.5999296,94.3583504
0.25726012545689
0
Hill cutting roadside drain

Progress Update : 22/03/2018
Construction in progress
Phase 1
eeukld
24.60136927857895,94.35635835092148
24.6008186,94.3572241
0.10681567666849
0
Hill cutting roadside drain in progress

Progress Update : 22/03/2018
Construction in progress
Phase 1
eeukld
24.60136927857895,94.35635835092148
24.598716,94.3610901
0.56202413592
0
Hill cutting roadside drain in progress

Progress Update : 22/03/2018
Construction in progress
Phase 1
eeukld
24.60136927857895,94.35635835092148
24.5825206,94.3483127
2.2481053054924
0
Hill cutting roadside drain